Week 1, Day 1
Another collaboration with Longview Builders to repair the damage caused when a huge oak tore off the entire front porch of this Kenilwoth bungalow.
Week 1, Day 4
After completing the foundation in two days, we were able to install the floor joists and get started on the main beams.
Week 2, Day 7
New roof and repairs on the existing house are complete. After the siding and ceiling are finished we begin the columns and handrails.
Week 2, Day 14
The new formed front steps, paint, and landscaping are finished. Good as New!